Planning example: Solar Surplus Mining Project
This is an illustrative planning scenario, not a completed customer project. The site, equipment and figures are assumptions for discussion, not measured results. Any implementation requires a site assessment and an individual technical proposal.
ForMiners structured a comparison between export value and estimated mining economics, then scoped miner count against available surplus kW and operating hours.

Country
EU
Energy source
Solar surplus electricity
Deployment
Flexible ASIC load for surplus monetization
Heat reuse
No heat reuse assumed; summer heat rejection and ventilation require separate engineering.
Project frame
Problem and solution
Problem
The site wanted to compare low-value grid export with a controllable mining load during recurring surplus production periods.
Solution
ForMiners structured a comparison between export value and estimated mining economics, then scoped miner count against available surplus kW and operating hours.
Results
What this planning case demonstrates
- Defined a conservative export-versus-mining comparison model.
- Estimated miner count based on surplus power rather than full site capacity.
- Prepared a pilot-first path for validation before scale-up.
Surplus capacity
120 kW
Seed planning value for calculator and layout examples.
Flexible load
28 miners
Illustrative count based on surplus-window planning.
Comparison baseline
Grid export
Mining scenario compared against tariff value.
Deployment data
Equipment and operating assumptions
Equipment
- ASIC miners matched to surplus windows
- Power controls
- Monitoring
- Optional container concept
Capacity
- Capacity
- 120 kW
- Miners
- 28
- Deployment
- Flexible ASIC load for surplus monetization
This concept illustrates a possible setup. Figures are calculation inputs, not measured customer results. We assess equipment and economics for your site individually.
Related case studies
More project examples

Illustrative cover, not a photograph of the project.
Residential heat reuse
Finland: ASIC heat integration for a 600 m² home
An immersion bath sized for six Antminer L9 transfers heat to a boiler serving a 600 m² home. Owner-reported installation facts, without a claim of measured savings.
- Energy
- Electricity; tariff at installation approximately €0.06/kWh
- On-site installation work was completed in two days, according to the owner. Design, procurement and the complete commissioning schedule are outside that period.
- The owner reports an immersion-loop temperature of up to 55°C. This is not a guaranteed tap-water or heating-delivery temperature.

Wind-energy site
Lithuania Wind-Site Mining Integration
Custom generation-tracking software adjusts the power of 3–4 immersion-cooled miners per turbine as available wind energy changes.
- Energy
- Wind generation and site electricity
- Brought container, cooling and ASIC equipment into one field deployment workflow.
- Validated service access and on-site configuration before ongoing operation.

Greenhouse
Tulip Greenhouse Heating Concept
Assess mining heat as a controllable input for winter greenhouse demand before investing in scale.
- Capacity
- 180 kW
- Miners
- 42
- Energy
- Grid power with heat reuse potential
- Created a heat-first evaluation framework for greenhouse economics.
- Highlighted humidity, airflow and crop-safety requirements before hardware selection.