Solar Surplus Mining Project
ForMiners structured a comparison between export value and estimated mining economics, then scoped miner count against available surplus kW and operating hours.

Country
EU
Energy source
Solar surplus electricity
Deployment
Flexible ASIC load for surplus monetization
Heat reuse
No heat reuse assumed; summer heat rejection and ventilation require separate engineering.
Project frame
Problem and solution
Problem
The site wanted to compare low-value grid export with a controllable mining load during recurring surplus production periods.
Solution
ForMiners structured a comparison between export value and estimated mining economics, then scoped miner count against available surplus kW and operating hours.
Results
What this planning case demonstrates
- Defined a conservative export-versus-mining comparison model.
- Estimated miner count based on surplus power rather than full site capacity.
- Prepared a pilot-first path for validation before scale-up.
Surplus capacity
120 kW
Flexible load
28 miners
Comparison baseline
Grid export
Deployment data
Equipment and operating assumptions
Equipment
- ASIC miners matched to surplus windows
- Power controls
- Monitoring
- Optional container concept
Capacity
- Capacity
- 120 kW
- Miners
- 28
- Deployment
- Flexible ASIC load for surplus monetization
This concept illustrates a possible setup. Figures are calculation inputs, not measured customer results. We assess equipment and economics for your site individually.
Related case studies
More project examples

Wind-energy site
Lithuania Wind-Site Mining Integration
A field-proven integration of container, ASIC and thermal infrastructure at a live wind-energy site.
- Energy
- Wind generation and site electricity
- Brought container, cooling and ASIC equipment into one field deployment workflow.
- Validated service access and on-site configuration before ongoing operation.

Greenhouse
Tulip Greenhouse Heating Concept
Assess mining heat as a controllable input for winter greenhouse demand before investing in scale.
- Capacity
- 180 kW
- Miners
- 42
- Energy
- Grid power with heat reuse potential
- Created a heat-first evaluation framework for greenhouse economics.
- Highlighted humidity, airflow and crop-safety requirements before hardware selection.

Mobile/container mining
Mining Container Deployment
Deploy modular mining capacity faster with infrastructure sized around power, cooling and service access.
- Capacity
- 500 kW
- Miners
- 120
- Energy
- Grid or excess-energy site connection
- Estimated maximum miner count from usable power and cooling derating.
- Mapped container size options for staged deployment.